Complaint #8641 — D.D. Mangalan Davies
Filed: 24 Nov 2014 ·
Address: —
I booked a flat in Cochin in the month of October 2008 by paying an amount of Rs.1,00,000/- when the piling was going on at the project site. The first installment (Rs.6,27,584/-) paid by me in the month of January 2009. As per the registration contract the due date for handing over of the flat was October 2011 (after 29 months + 6 months grace period) as per the agreement. Whereas the flat actually handed over in July 2013. Thus, there was 1 year and 9 months delay. Hence I want the builder to compensate the amount on the basis of the figures mentioned in the 'Agreement of Sale'.
During my private talk with two of the owners they told me that they have already got the said compensation.
Also due to fault plastering work all the painting got damaged. For doing the rectifying that damage I need another 30,000/- rs. I need compensation for this also.