Complaint #767 — Keshav Dayalani

Filed: 4 Mar 2013  ·  Address: Vietnam
Dear Sir, I am an NRI customer. • I booked and apartment in January 2008 at Puri Pranayam, Faridabad under construction linked plan. • Buyer agreement was signed in June 2008 with a promise to hand over the apartment in 36 months with a grace period of 6 months (42 months in total). • The aforesaid period of 42 months ended in December 2011. • I have made all payments on time and paid 100% of value. • Possession was offered in January 2013. • Company officials kept assuring that delay compensation would be settled at the end. All such assurances were verbal while they avoided giving any written assurance. • The company is now refusing to compensate for delay (approximately 13 months) Please advise me on the above matter. Regards, Keshav.