Complaint #1795 — Rishabh Arora
Filed: 20 Jul 2013 ·
Address: —
I had bought a ground floor E-56 in ABW Aditya Niketan, Manesar, 2 years ago. Till date the construction for the same has not been started.
There is a case with Civil Writ Petition bearing No. 23769 of 2011 titled “ Om Prakash & others Vs State of Haryana and others” pending before the Hon’ble High Court of Punjab and Haryana at Chandigarh and the dates keep extending again and again.
In 1993, the Supreme Court ruled in favour of MK Gupta in his case against the Lucknow Development Authority for not delivering his flat on time. This landmark judgement brought housing construction under the purview of the Consumer Protection Act, 1986.
The court observed: \"When a statutory authority develops land or allots a site, or constructs a house for the benefit of a common man, it is \'service\' by a builder or contractor... When possession of the property is not delivered within the stipulated period, the delay so caused is denial of \'service\'. Such disputes or claims are not with respect to t